A new pickleball court in the St. Louis area runs about $25,000–$45,000 per court on asphalt and $45,000–$80,000 or more on post-tension concrete, according to the Midwest ranges published in 2026 by Byrne & Jones, a St. Louis–based sports construction firm. National residential guides put a typical 30 × 60-foot backyard court at $20,000–$50,000. Converting a tennis court to four pickleball courts is $5,000–$15,000; a full resurfacing is $4,000–$8,000. These are published ranges from third parties — not our prices — and your written quote is built from your site.
The published numbers in one table
| Project | Published range | Basis | Source, date |
|---|---|---|---|
| New court — asphalt | $25,000 – $45,000 per court | Base, paving, acrylic color system, net posts, lines; Midwest commercial | Byrne & Jones, page updated June 2026 |
| New court — post-tension concrete | $45,000 – $80,000+ per court | Base, PT slab, acrylic color system, net posts, lines; Midwest commercial | Byrne & Jones, June 2026 |
| Tennis-to-pickleball conversion | $5,000 – $15,000 | Layout, surfacing, striping, nets, fencing modifications | Byrne & Jones, June 2026 |
| Full resurfacing | $4,000 – $8,000 per court | Clean, crack repair, resurfacer, color, restripe | Byrne & Jones, June 2026 |
| Color coat and restripe | $3,000 – $6,000 per court | Acrylic color + lines | Byrne & Jones, June 2026 |
| Typical backyard court (30 × 60) | $20,000 – $50,000 | National residential; average $34,000 | HomeGuide, Jan 6 2026 |
| Typical backyard court | $20,000 – $50,000 | National residential; average $34,000 | Angi, Aug 3 2026 |
| Installed cost per square foot | $11 – $28 | National residential | HomeGuide, Jan 2026 |
| Concrete slab (base only) | $5 – $10 per sq ft | National | HomeGuide, Jan 2026 |
| Asphalt (base only) | $5 – $12+ per sq ft | National | HomeGuide, Jan 2026 |
| Hard acrylic surface | $0.50 – $1.00 per sq ft | National | HomeGuide, Jan 2026 |
| Cushioned acrylic surface | $2 – $4 per sq ft | National | HomeGuide, Jan 2026 |
| Court fencing | $2,000 – $6,000 | National | HomeGuide, Jan 2026; Angi, Aug 2026 |
| Court lighting | $5,000 – $10,000 | National; typically 2 or 4 poles ~20 ft | HomeGuide, Jan 2026 |
| Court lighting | $2,000 – $10,000 | National | Angi, Aug 2026 |
| Resurfacing a 30 × 60 pad | $1,500 – $3,500 | National | HomeGuide, Jan 2026 |
| Tennis → four pickleball courts | $5,000 – $20,000 | National | HomeGuide, Jan 2026 |
One older local data point: in 2021, St. Louis Magazine, drawing on the head of a St. Louis paving firm's sports-construction department, reported that a new backyard pickleball court — leveling, concrete, color coating, fencing, lighting, benches, landscaping and nets — "could run up to $35,000 and take a couple months to build." Treat it as a 2021 figure.
Why the ranges are so wide
A $25,000 court and an $80,000 court are both real. The difference comes from five things.
1. The slab. This is the single biggest line. Post-tension concrete costs more than asphalt — the midpoints of Byrne & Jones's published ranges differ by about $27,500 per court, and their blog puts asphalt at 20–30% less to install — because it means forms, steel tendons, stressing equipment and a crew that knows the system. It also lasts longer; see below.
2. The ground. A flat, well-drained lawn costs least. A slope means cut, fill and maybe a retaining wall. Poor soil means a deeper stone base. Every foot of grade change shows up in the quote.
3. Access. A 10-foot side gate lets a skid steer and concrete truck chute in. No access means a concrete pump, a smaller machine, or hand work, and each costs more.
4. Size and count. A 34 × 64 pad has 21% more surface than a 30 × 60. Two courts side by side don't cost twice one court — mobilization and base work are shared, and Byrne & Jones notes multi-court projects cost significantly less per court.
5. Add-ons. Fence height and length, windscreen, acoustic panels, lighting, cushioned surface, a basketball goal, benches, shade, landscaping, and the electrical run from your panel.
What pushes St. Louis costs up
Three local conditions add cost that a warm, sandy site wouldn't:
- Frost depth. Fence posts, net posts and light poles have to be footed below 30 inches here (the depth cited for St. Louis County and written into St. Charles County's residential code).
- Clay. The Missouri Geological Survey's study of St. Louis County recorded clay swelling pressures above 3,300 pounds per square foot. Building for that — a better base, or post-tension — costs money that a sandy site doesn't need.
- Permits and review. With about 89 governing authorities in St. Louis County alone, some projects need planning commission or architectural review, fence permits, grading permits or a stormwater practice. Kirkwood, for example, requires a drywell or similar practice once a project adds 1,000 square feet of impervious surface — see the stormwater guide and the permits guide.
Asphalt versus post-tension over 25 years
Up-front price isn't the whole cost. Using Byrne & Jones's published figures:
| Asphalt | Post-tension concrete | |
|---|---|---|
| New court (per court, Midwest commercial) | $25,000 – $45,000 | $45,000 – $80,000+ |
| Typical life before major rehabilitation | 15 – 20 years | 30 – 40+ years |
| Acrylic resurfacing interval | 4 – 8 years (most acrylic courts) | 8 – 10 years |
| Control joints in playing area | n/a (cracks instead) | None |
Over 25 years, an asphalt court is likely to need three to six resurfacings and, at a 15–20-year life, a major rehabilitation; a post-tension court, two or three resurfacings. At $4,000–$8,000 per resurfacing, the gap closes but doesn't disappear. The stronger argument for post-tension in St. Louis is fewer cracks between resurfacings. The engineering is in post-tension vs asphalt vs concrete.
What should be in a court quote
A written quote you can compare should list each of these as a line:
- Site preparation and excavation (including spoil haul-off)
- Base material and compacted depth
- Slab type and thickness (and, for post-tension, tendon spacing and who designs it)
- Drainage: slope, edge drains, drywell or other stormwater practice
- Cure period before coating
- Surface system: brand, number of resurfacer and color coats, cushion layers
- Lines and net system
- Fence: height, length, gauge, coating, post footing depth
- Windscreen or acoustic panels
- Lighting: fixtures, poles, footings, electrical run, controls
- Permits: which ones, who applies, who pays the fees
- Restoration: topsoil, seed or sod, damaged lawn
- Exclusions, payment schedule, schedule and warranty terms
Our quote comparison tool and the downloadable quote comparison checklist put those lines side by side.
Costs people forget
- Survey. If your lot lines are unclear, a boundary survey before you build is cheaper than a dispute after.
- Stormwater practice. In cities with a trigger like Kirkwood's, a drywell or rain garden is part of the project.
- Tree work. Removing a tree or roots in the court footprint; keeping leaf litter off later.
- Electrical. The run from your panel to the court for lights, and possibly a panel upgrade.
- Restoration. Equipment tracks across a lawn leave damage.
- Maintenance. Cleaning, leaf removal and resurfacing every several years. Budget for it.
Three worked examples
These use the same published figures as our instant quote, with lows rounded down and highs rounded up to the nearest $500. They exclude site-specific lines: unusual grading, retaining walls, stormwater practices, tree work, the electrical run and permit fees.
| Project | Lines | Published-range total |
|---|---|---|
| Asphalt court, 30 × 60, with fence | $25,000–$45,000 court + $2,000–$6,000 fence | $27,000 – $51,000 |
| Post-tension court, 34 × 64, with fence and cushioned surface | $45,000–$80,000+ court + $2,000–$6,000 fence + cushion upgrade at $1.00–$3.50/sq ft × 2,176 sq ft | $49,000 – $94,000+ |
| Converting two subdivision tennis courts to eight pickleball courts | $5,000–$15,000 per tennis court × 2 | $10,000 – $30,000 |
The cushion upgrade is the difference between HomeGuide's cushioned ($2–$4) and hard ($0.50–$1.00) acrylic prices per square foot. The conversion line assumes sound slabs; failing slabs turn it into a rebuild.
Red flags in a quote
- No slab thickness or base depth. You can't compare what isn't stated.
- No cure time before coating. New concrete needs about 28 days; asphalt about 30, per coating manufacturers.
- Fence posts with no footing depth. In St. Louis they belong below 30 inches.
- "Permits by owner" with no list. You should know which approvals your court needs before you sign.
- A total far under the published low end with no explanation of what's left out.
How to use these ranges
Use the published ranges to set a budget and to sanity-check quotes, not as a price. A quote far below the low end usually leaves something out — often the base, drainage, footing depth or permits. A quote far above usually reflects a hard site or a premium package. The instant quote turns these ranges into a ballpark for your project type, slab and add-ons.
Frequently asked questions
What's the cheapest way to get a court? Painting lines on an existing driveway or a sound slab of the right size, with a portable net. After that, an asphalt court on a flat, easy-access lot.
Is a cushioned surface worth it? For players with knee or back trouble, many think so. At $2–$4 per square foot against $0.50–$1.00 for hard acrylic (HomeGuide), it adds a few thousand dollars on an 1,800–2,176 square foot pad.
Do two courts cost twice as much? No. Mobilization and base work are shared, so the second court costs less than the first.
Does a court add value to a house? We don't have St. Louis sales data to answer that, and we won't guess. A court appeals to some buyers and not others.
How much is a tennis court conversion? $5,000–$15,000 per tennis court on published Midwest ranges, if the slab is sound. Boards weighing conversion against new courts will find a worked comparison in our HOA planning guide.
Sources
- Byrne & Jones — Midwest Pickleball Court Construction (cost table, fence heights, resurfacing interval, PT benefits, build times) — metadata 2026-06-11; accessed 2026-10-10
- Byrne & Jones — The Real Cost of Asphalt vs. Post-Tension Concrete Courts — pub. 2026-03-31, mod. 2026-05-13; accessed 2026-10-10
- St. Louis Magazine — "St. Louis–area yards have become the new rec centers" (Nicholas Phillips) — 2021-06-16 (mod. 2025-01-21); accessed 2026-10-10
- HomeGuide — Pickleball Court Cost — 2026-01-06; accessed 2026-10-10
- Angi — How much does it cost to build a pickleball court — 2026-08-03; accessed 2026-10-10
- NWS St. Louis — Frost/freeze page — 1991–2020 basis; accessed 2026-10-10
- Missouri Geological Survey — Engineering Geology of St. Louis County (EG-4, Lutzen & Rockaway) — 1971; accessed 2026-10-10
- Kirkwood — Residential Green Practices, App. F — rev. Nov 2024; accessed 2026-10-10
- St. Charles County — Residential Code §500.150 (frost 30) and §500.100/§500.920 (2021 codes) — Ord. 25-085 (2025-12-15); accessed 2026-10-10
- St. Louis County code edition: 2015 I-codes, Ord. 27,654 (via Crestwood, Pagedale, Oakland) — 2019-12-18 / eff. 2020-04-01; accessed 2026-10-10